SPOKANE, Wash. - Construction of the Mann-Grandstaff VA Medical Center's Intensive Outpatient Mental Health & Education Building expansion project has been postponed.

During the early stages of the project while excavating for the foundation, workers encountered a pit of gravel in the soil they had not foreseen during the planning phase.

The project intends to perform additional geotechnical testing on the soil before construction can continue.

Once this happens, the project will be resubmitted through the VA construction approval process for completion.

The Veterans Health Administration expects approval to be obtained and for the project to move forward in the future.
 